A contract is to install 450′ of duct that is purchased for $1.75 per foot. The job is estimated to take 5 hours at $45.00 an hour for a two man crew. The contractor wants to make a 15% profit on this job, how much should his bid be?

A contract is to install 450′ of duct that is purchased for $1.75 per foot. The job is estimated to take 5 hours at $45.00 an hour for a two man crew. The contractor wants to make a 15% profit on this job, how much should his bid be?