A construction project is to be completed in 70 days. The contractor has a liquidated damage clause of $150/day. The job is completed in 91 days. The architect gives a 4-day extension due to bad weather. What will the liquidated damages be?

A construction project is to be completed in 70 days. The contractor has a liquidated damage clause of $150/day. The job is completed in 91 days. The architect gives a 4-day extension due to bad weather. What will the liquidated damages be?