A contractor estimates the following direct costs on a job: Materials= $20,000 Sales Tax=6% Labor=$ 10,000 Overhead=50% of labor costs Contingencies=$ 1,000 Profit= 10% of total costs The total bid should be between _____.

A contractor estimates the following direct costs on a job: Materials= $20,000 Sales Tax=6% Labor=$ 10,000 Overhead=50% of labor costs Contingencies=$ 1,000 Profit= 10% of total costs The total bid should be between _____.