A contractor has a cost plus 12% contract for which previous progress payments have been received. Based on the following, how much should be submitted as the current billing? Line Item Cost to Date PreviousPmts Sitework 12,500 8,000 Concrete 8,400 5,500 Masonary 3,000 2,400