A contractor has a project that requires 96 man hours to complete and must be done in only three days. If eight-hour days are worked, what will be the minimum crew size required?

A contractor has a project that requires 96 man hours to complete and must be done in only three days. If eight-hour days are worked, what will be the minimum crew size required?