A contractor has not received agreed payment and must file a lein. Using the following information, what is the maximum amount that the lein can be filed? The original contract was for $12,000. A written change order to upgrade windows for $900 was appproved. A $100 increase in the building permit fee after contract signing was paid by the contractor who wants reimbursement. A formally agreed additional $400 for rain delay has not been signed by the owner.

A contractor has not received agreed payment and must file a lein. Using the following information, what is the maximum amount that the lein can be filed? The original contract was for $12,000. A written change order to upgrade windows for $900 was appproved. A $100 increase in the building permit fee after contract signing was paid by the contractor who wants reimbursement. A formally agreed additional $400 for rain delay has not been signed by the owner.