A contractor has scheduled 10 labor to work 8 hours per day. Based on a 5 day workweek for 4 weeks to meet a deadline each laborer makes $10 per hour. However he asks the contractor to complete the project in 3 we eks. The owner is willing to pay the necessary overtime. The contractor will work 5 days per week and use the original crew. Overtime distributed equally. What is the additional overtime?

A contractor has scheduled 10 labor to work 8 hours per day. Based on a 5 day workweek for 4 weeks to meet a deadline each laborer makes $10 per hour. However he asks the contractor to complete the project in 3 we eks. The owner is willing to pay the necessary overtime. The contractor will work 5 days per week and use the original crew. Overtime distributed equally. What is the additional overtime?