A contractor is calculating progress on a project now underway. His figures show total contract price of $129,700. The total estimated cost of $101,500. Cost to date $63,413. What is the percentage of completion for this contract?

A contractor is calculating progress on a project now underway. His figures show total contract price of $129,700. The total estimated cost of $101,500. Cost to date $63,413. What is the percentage of completion for this contract?