A hole is being excavated for a 32′ x 41′ hole. The hole is 5′ deep and 4′ of clearance is required beyond each of the building lines. The sides are not sloped. How many cubic yards of soil will be removed?

A hole is being excavated for a 32′ x 41′ hole. The hole is 5′ deep and 4′ of clearance is required beyond each of the building lines. The sides are not sloped. How many cubic yards of soil will be removed?