An estimate shows the following job items: Job #1, $2,800; Job #2, $4,100; Job #3 $6,100; Job #4 $3,800. Actual costs are Job #1 $2,300; Job #2 $4,400; Job #3 $6,300; Job #4 $3,300. This portion of the project is: