Estimated/actual cost for a job just completed are: labor-$5,200/$5,600; material-$10,800/$8,700; subcontractors-$2,000/$1,600; overhead $1,000/$975. This job was completed:

Estimated/actual cost for a job just completed are: labor-$5,200/$5,600; material-$10,800/$8,700; subcontractors-$2,000/$1,600; overhead $1,000/$975. This job was completed: