Fifteen AMP branch circuits will be used for lighting branch circuits. What is the minimum required number of 15 AMP branch circuits required to serve the computed branch circuit lighting load for a 3,200 square foot house which includes a 400 square ft garage and 1,400 square foot floor and 1,400 square foot unfinished basement that is adaptable to a future use. The service 120/240 volt.

Fifteen AMP branch circuits will be used for lighting branch circuits. What is the minimum required number of 15 AMP branch circuits required to serve the computed branch circuit lighting load for a 3,200 square foot house which includes a 400 square ft garage and 1,400 square foot floor and 1,400 square foot unfinished basement that is adaptable to a future use. The service 120/240 volt.