Given: Job cost accounts show a contractor that direct costs from a previous job were $21,000. Overhead costs for that job were $1,200. The contractor is now estimating an identical job. However, the contractor`s direct cost have increased 5% and overhead costs have increased 3%. What will be the estimated cost of the new job? (Use only the figures in percentages above.)

Given: Job cost accounts show a contractor that direct costs from a previous job were $21,000. Overhead costs for that job were $1,200. The contractor is now estimating an identical job. However, the contractor`s direct cost have increased 5% and overhead costs have increased 3%. What will be the estimated cost of the new job? (Use only the figures in percentages above.)