If a worker is paid $7.90 per hour and works 12 hours to form 100 sq. ft. of a slab; what is the cost per sq.ft. ?

If a worker is paid $7.90 per hour and works 12 hours to form 100 sq. ft. of a slab; what is the cost per sq.ft. ?