Ten employees have been scheduled to work 8 hours per day (based on a 5 day work week) for 3 weeks to meet a deadline. Each employee makes $15 per hour. The owner is willing to pay overtime to get the job done in 2 weeks with the 5 day work week unchanged. How much extra will the owner have to pay for the new deadline?

Ten employees have been scheduled to work 8 hours per day (based on a 5 day work week) for 3 weeks to meet a deadline. Each employee makes $15 per hour. The owner is willing to pay overtime to get the job done in 2 weeks with the 5 day work week unchanged. How much extra will the owner have to pay for the new deadline?