The following information was determined from a construction bar chart. Excavation & grading-May to June. Foundations, formwork, walls-May to Aug. Rebar-June to Sept. Concret-June to Sept. Suspended slabs-July to Aug. Slab on grade-July Plbg UG-May to Sept. Plbg AG-June to Feb. Electrical UG-May to Oct. Electrical AG- June to Feb. Mechanical A/C-Aug to Feb. Roofing-Sept to Oct. Lath & plaster-July to Nov. Millwork, doors, windows-Oct to Feb. Painting-Nov to Feb. Paving, landscaping, parking-Jan toFeb. Hardware-Oct to Feb. Final inspection, pickup-Feb. What statement is true regarding electrical work?

The following information was determined from a construction bar chart. Excavation & grading-May to June. Foundations, formwork, walls-May to Aug. Rebar-June to Sept. Concret-June to Sept. Suspended slabs-July to Aug. Slab on grade-July Plbg UG-May to Sept. Plbg AG-June to Feb. Electrical UG-May to Oct. Electrical AG- June to Feb. Mechanical A/C-Aug to Feb. Roofing-Sept to Oct. Lath & plaster-July to Nov. Millwork, doors, windows-Oct to Feb. Painting-Nov to Feb. Paving, landscaping, parking-Jan toFeb. Hardware-Oct to Feb. Final inspection, pickup-Feb. What statement is true regarding electrical work?