Worker A is paid $15.00 per hour and worker B is paid $12.50 per hour. A particular task project is estimated to be completed in 35 units of work. For every five units, Worker A will use 0.75 hours of time and worker B will use .25 hours of time. How much money should be bugeted for direct labor on this task?

Worker A is paid $15.00 per hour and worker B is paid $12.50 per hour. A particular task project is estimated to be completed in 35 units of work. For every five units, Worker A will use 0.75 hours of time and worker B will use .25 hours of time. How much money should be bugeted for direct labor on this task?